    sape sape boleh tolong?

    Activity Time (weeks) Immediate Predecessors
    1- collect requirements 2 -
    2- analyze processes 3 1
    3- analyze data 3 2
    4- design processes 7 2
    5- design data 6 2
    6- design screens 1 3, 4
    7- design reports 5 4, 5
    8- program 4 6, 7
    9- test and document 8 7
    10- install 2 8,9
    a. Calculate the earliest expected completion time
    b. Draw the GANNT and PERT charts for the activities
    c. Show the critical path in the PERT chart.
    d. Will the critical path change if Activity 6 was revised to take six weeks instead of one week?

  2. #2
    Senior Member
    Nett8's Avatar
    Join Date
    Oct 2007
    Location
    Damansara, Petaling Jaya
    Posts
    4,295
    Post Thanks / Like
    kenapa tak guna microsoft project jer... cepat dan tangkas... siap ada milestone progress...

  3. #3
    Senior Member
    grankie's Avatar
    Join Date
    Aug 2009
    Location
    nyok tree
    Posts
    1,515
    Post Thanks / Like
    Blog Entries
    1
    ya la ni memang kerja microsoft project

  4. 07-11-12, 10:25 PM

  5. #4
    Junior Member
    Join Date
    Apr 2008
    Posts
    15
    Post Thanks / Like
    x phm yg a,c,d tu..help?

  6. #5
    Senior Member
    grankie's Avatar
    Join Date
    Aug 2009
    Location
    nyok tree
    Posts
    1,515
    Post Thanks / Like
    Blog Entries
    1
    tu kena tanya pakar... lama x guna project tuk database ni .tolong tuan tanah anyone?

  7. #6
    Junior Member
    Join Date
    Apr 2008
    Posts
    15
    Post Thanks / Like
    yup..anyone.sape yg pakar sini

  8. #7
    Junior Member
    Join Date
    Sep 2010
    Posts
    25
    Post Thanks / Like
    yg a 2 xbrape phm....yg c n d 2 berdasarkan b kot....ce try wat GANNT and PERT charts 2 dlu brdasarkan data...(Activity=Time (weeks)/Immediate Predecessors....pastu highlightkan yg critical part dlm pert chart 2....kre yg boleh mengjangkau masa yg ditetapkan mengikut perancangan....pastu wat chart bru utk d...(tkr data aktivity 6)...bandingkan ngan c....pastu tgk critical part ada yg berubh x??then siap....kalu xsalahla.....kalu slah im sorry....

  9. #8
    Junior Member
    Join Date
    Apr 2008
    Posts
    15
    Post Thanks / Like
    Quote Originally Posted by saufiemauludi View Post
    yg a 2 xbrape phm....yg c n d 2 berdasarkan b kot....ce try wat GANNT and PERT charts 2 dlu brdasarkan data...(Activity=Time (weeks)/Immediate Predecessors....pastu highlightkan yg critical part dlm pert chart 2....kre yg boleh mengjangkau masa yg ditetapkan mengikut perancangan....pastu wat chart bru utk d...(tkr data aktivity 6)...bandingkan ngan c....pastu tgk critical part ada yg berubh x??then siap....kalu xsalahla.....kalu slah im sorry....
    try dlu..thanks

  10. #9
    Senior Member
    Nett8's Avatar
    Join Date
    Oct 2007
    Location
    Damansara, Petaling Jaya
    Posts
    4,295
    Post Thanks / Like
    bro cuba guna microsoft project tgk... key in dulu, data-data berserta tempoh kejer tu... http://www.project-tutorial.com/

  11. #10
    Junior Member
    Join Date
    Apr 2008
    Posts
    15
    Post Thanks / Like

    Server sponsored by SyokHost.Com

    Server sponsored by SyokHost.Com

    Server sponsored by SyokHost.Com

    Server sponsored by SyokHost.Com
    Quote Originally Posted by Nett8 View Post
    bro cuba guna microsoft project tgk... key in dulu, data-data berserta tempoh kejer tu... http://www.project-tutorial.com/
    ok bro.thanks

Members who have read this thread: 0

There are no members to list at the moment.

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •